Master en-suite shower |
Bath frame in master en-suite |
Master en-suite shower tray |
Hall |
Stairs and hall |
Shower room shower tray |
Shower room shower |
Guest en-suite floor and shower |
Utility room |
Tor is back on site this coming weekend for a extended weekend trip and as usual has a full work schedule for the weekend. Monday 3rd June will be a busy day with the electricians starting second fix, the MVHR system being commissioned, oak flooring being delivered ( +/- 520 boards to move into the house by hand!) and hopefully our granite work tops for the kitchen are delivered and installed. Now that the tiling is completed we can start second fix on the plumbing as well - maybe this trip if things go well.