Thursday, 6 June 2013

Granite Counters Installed

Just back from a busy 4 days onsite. Over the weekend Tor & Bill worked away on the rain water harvesting (RWH) system, MVHR system and UFH system on Saturday & Sunday.

This included wiring up the submersible pump in the RWH tank that will supply water to the toilets and the pump controller along with a bit of dangling upside down in the top of the tank as well to hook up the pump.

RWH pump controller
 On the MVHR system the remote control panel was wired in, the final valves installed, connections made to the unit and insulation installed on the exhaust and intake ducts.

For the UFH system two of the control centres were wired up and actuators installed on all four manifolds.

Utility room UFH controller
 On Monday the MVHR system was commissioned with the flow rates to the various rooms being set and correct function of the booster switches and remote panel confirmed. While this was on going I worked on some of the plumbing in the master en-suite. The other big thing on Monday was the delivery of the oak flooring for the house. We rented in a forklift to offload the pallets from the lorry but it all had to be carried inside by hand. This took me all afternoon to do -  well it was 690 boards ( or 4.5 MT/ 10,000 lbs) after all!. Before leaving that day I also leveled various floor areas in preparation for laying the floor. Phew, no wonder I was knackered that night!

Tuesday was only a bit quieter, but no much. early in the morning the granite counter tops arrived as did the electricians. After getting the sparkies started I helped move the large island granite top into place and checked on the installation in general. The granite tops look as good as we expected and the whole colour scheme work well.

Granite counter top being installed

Installed counters on bow fronted units

Whole kitchen

Kitchen sink
Island with drop down area

After the counter tops were in I spent a couple of hours sorting out the fittings for the electricians and then got back to the master en-suite plumbing again. Still a bit more of this to do but I think I have broken the back of it now

Wednesday, 29 May 2013

Tiling is complete

Well almost!. There are some small bits and pieces that still need finished off (feels like everything is that way at the moment) but all floors and walls that needed tiled are no completed and grouted.

Master en-suite shower

Bath frame in master en-suite

Master en-suite shower tray

Hall

Stairs and hall

Shower room shower tray

Shower room shower

Guest en-suite floor and shower

Utility room
Heidi is just back from a full on weekend of painting and directing of operations. The lounge, dining room, and utility room are now painted which means the ground floor is about 70% painted now.

Lounge alcoves

Lounge looking to dining room

Dining room looking to kitchen

Tor is back on site this coming weekend for a extended weekend trip and as usual has a full work schedule for the weekend. Monday 3rd June will be a busy day with the electricians starting second fix, the MVHR system being commissioned, oak flooring being delivered ( +/- 520 boards to move into the house by hand!) and hopefully our granite work tops for the kitchen are delivered and installed. Now that the tiling is completed we can start second fix on the plumbing as well - maybe this trip if things go well.


Sunday, 26 May 2013

Kitchen units installed

A successful weekend a couple of weeks ago getting the kitchen units installed.

Island units

Cabinets to left of where range will be positioned

....and to right


We also had a look at the rain water harvesting pump and control system which was good as some additional cable was needed to get everything back into the house. Sod's law being what it is we were just a couple of meters short.

The tilers have also been busy the last couple of weeks and most of the tiling is now complete and the stairs is progressing again with the balcony trim and newel posts now being installed. Heidi is back this weekend painting and having the templating done for the granite counter top and glass splash backs completed.

We have also been busy working out what we want for doors, skirting, architrave and door handles so the final bits and pieces are now decided. Just a case of getting things delivered and installed now -  end of August completion is still looking like a very realistic date.

Will add more pictures when Heidi gets back on Tuesday

Tuesday, 7 May 2013

Driveway finished

A quick up date with some pictures of the finished driveway which looks good but will require some changes to be made to the tarmac area as the contractor didn't follow the drawings!

We weren't expecting the tarmac to look like that!

Granite setts with the fan pattern

Another view of the setts and fan pattern
Back over in two days time with the familiy to take delivery of the kitchen units and see the driveway in person.

Thursday, 2 May 2013

Stair is installed

Just back just back from another weekend of working on the house following only a couple of weeks behind Heidi who also had a solo trip back.

Things have really been moving on in the last month since we were back as a family at Easter. For Heidi's trip saw her getting on with some more painting getting the kitchen completed and finishing off the master bedroom. Distracting her from her work we had the fire place being installed, tilers in putting in the first floor tiles in the study, the joiner working on loft hatches and access ladder installation, and the data engineer was back starting to fit up outlets and cutting holes for speakers in the ceiling. Outside we had the landscapers finalising the pavers and the driveway installers getting started. No surprise Heidi didn't get quite as much painting done as she had hoped!

Driveway taking shape
Bathroom tiles going down
 The week after Heidi was there dad was up on site for us as the stairway people finally got to site. The stair installation went pretty smoothly with no major problems and the main flight is no in place. They are back again this week to start installing newel posts and hand rail.

Oak stair flight in
The same week the GSHP service engineer also finally made it out to us and found the problem with the unit. Turned out to be a loose connection within the unit that was causing all the problems.

Hot on the heels of the stairs going in Tor was back fitting shower trays and doing other bits and pieces to get the other rooms ready to tile. On site were also Bill & Evelyn - Bill wiring up UFH thermostats, central vacuum sockets and MVHR booster switches and Evelyn painting in bathrooms. Thanks mum & dad for all your help. A successful weekends work all round and things are starting to look like to are heading towards completion now.

This week the data engineer is back fitting speaker, CCTV cameras, PIRs for the security system and terminating CAT6 HD cables. The tilers are also back working in the kitchen in preparation for the kitchen units being delivered on 10th May. Outside the drive way works are completing....busy times!

We are back in week as a family to take delivery of the kitchen units and to get them installed, plus more painting. The list of things to do is getting shorter......very slowly.

Plan is still to be finished by the end of August so we are in the last few months of frantic activity, then we can worry about other things!

Friday, 5 April 2013

Landscaping works ongoing

The landscapers have been working away all week with the gate pilars and pavers and are making good progress. By the time Heidi is back next Thursday I expect they will have all the pavers down front and back and the driveway should be under way.

Second coarse on gate pillars

Pavers outside kitchen


Pavers through the pend


With the stairs hopefully starting to go in and tiling starting at the same time its going to be a busy week or two coming up and some very visual progress happening. Its all very exciting as we finally see the house reaching the finishing stages

A busy Easter week

We are less than a week home from our last trip back to Aberdeen and another busy work week on the house. Things are definitely feeling like we are heading into the finishing stretches now and Heidi has been spending a lot of time looking for tiles for various rooms but I think we are finally there now.

We had a very varied work scope during our week back with painting, ground works, plumbing and carpentry on the list of things to do. I started off by getting the shower areas in the shower room and master en suite ready for laying concrete bases and ultimately the shower trays. Things didn't get off to a good start as I put the grinder blade through a water pipe!. Having recovered from this things progressed well with this work and the concrete bases are now laid and are drying out before the shower trays are laid. While I was doing this Heidi and the boys started to give the master bedroom its first of 3 coats of paint. The first 2 coats prime and seal the plaster and the last coat gives the final finish.

Master ensuite shower tray area

Shower room shower tray area

Master bedroom with one coat of paint


On the Sunday Heidi entertained the boys after they complained mightily the day before about being on site. This left me alone on site so I spent the day securing pipe work in the storage room area and re instating the step area there. Something I had pulled up a long time ago so good to see it back down again finally.

We progressed onto our civil works on Monday, digging trenches with a mini digger and laying electrical cables to the driveway gate pillars and water pipe to a couple of external tap locations. The weather thankfully cooperated and we got this work done without any really issues. While I had the digger I also took the opportunity to locate our lost telecoms duct.

Tor with "helpers" on digger
Tuesday was short day with a meeting with the landscaping people to finalise the paving and driveway works that were about to commence. that afternoon we headed down the road to mum & dad's house to drop the boys off and use it as a spring board for driving to Middlesborough the following day to select the granite for our kitchen island and counter tops

The trip to the granite supplier was a long one but well worth the effort. They had some amazing pieces of rock at there factory and we found what is certainly a very different piece of rock. Heidi & I both gravitated to this rock as we wander amongst the multitude of slabs available. Its been great how aligned we are with most of these types of decisions. On our way back up the road we stopped at a tile show room in Glasgow to have a look at some different options. A bit like the granite we had some initial ideas going into the meeting but by the time we left there had been some adjustments in our thinking.

The kitchen island granite
Being child free for a few days we divided and conquered with Heidi heading up the tile hunt in Aberdeen and myself continuing with work on site. First on the list was pouring the concrete for the shower trays, then it was onto fitting up the last of the central vacuum pipe work in the house and making various electrical connection for that and the MVHR system.

Getting the main family bathroom ready for tiling was a priority and this we successfully accomplished with a bit more plumbing and joinery work along the way. The shower tray was also successfully laid, unlike the guest en suite where I had issues due to the space that was left being rather too tight - after a few days of reflecting on it I now have a plan forward for this as well. The other priority was painting the ceiling over the stair area before the stair went in. The access being much easier without the stairs being there. Another successful result here was achieved.

Painting the main hall ceiling

Family bathroom shower tray
On Good Friday our landscapers were back to start their works. The first thing they got going with was the foundations for the gate pillars. This included setting the steel columns I will use to hang the gates off being set into the concrete as well.
Steel column for hanging gates
 They also managed to make a start to the back patio with the granite step being installed outside the kitchen door and the first granite pavers being laid in the same area. Our drive was starting to look like a granite dealers yard by this point with granite lintels, setts and pavers all being on site.

Half the granite in the drive