The north roof slate work is now complete and the slating will now take a break until the scaffolding over the utility room and boiler room section is gone.
Entrance flat roof |
Quentin finishing off the last section on the main roof |
The lead work for the flat roof over the entrance way also started at the end of the week
Lots of detailed work in the flat roof |
The larch cladding on the main wall sections is progressing and should be completed by the middle of next week.
Cladding around Ewan's windows |
On Friday we had the last of the ground floor windows delivered along with 3 doors. Unfortunately 2 of the doors are for the garage, which hasn't started yet. The remaining doors will arrive the next week.